| Inverter limit | 800 W |
|---|---|
| Panels | Not fixed nationally; some grid operators expect at most 800 Wp for the simple route |
| Registration | Notify your grid operator at least two weeks before you start |
| Batteries | Notify as part of the system; details differ by grid operator |
| Tenants and owners | Tenants: clear it with the owner first. Owner occupied flats: since 1 September 2024 consent counts as given if the other owners are informed and do not object within two months |
Systems with a total output of at most 800 W per grid user count as very small generating plants (Kleinsterzeugungsanlagen, section 6 (1) no. 78 of the new Electricity Industry Act ElWG, as cited by E-Control). No permit is needed, but the grid operator must be told at least two weeks in advance, usually through its online portal. Above 800 W a grid access contract is needed.
An automatic disconnection device is required under TOR Erzeuger Type A; E-Control advises asking for a certificate of conformity from a certified test body. Never use extension leads or power strips; a fixed socket only if the maker approves it. Zero VAT on PV modules, balcony systems included, ended on 31 March 2025 (until 31 December 2025 only for contracts before 7 March 2025).
What a balcony system produces here
| City | Panels | South, 35° | South, vertical | West, vertical | Own use and savings (south, vertical) |
|---|---|---|---|---|---|
| Vienna | 800 Wp | 906 kWh | 640 kWh | 445 kWh | 408 kWh, €122.49 |
Guides for this country
Not yet confirmed
- Date of entry into force of the new ElWG and whether any state currently funds plug in systems.
Sources
- E-Control: Mini PV Anlagen, FAQ official
- oesterreich.gv.at: Selbsterzeugung von Strom (updated 1 October 2026) official
- BMF: Steuersatz für Photovoltaikmodule (updated 1 January 2026) official